Magnox Electric Ltd’s main focus over the next three years will be maintaining Sizewell A’s excellent safety record and commencing the site’s Defuelling and Decommissioning programme.
Preparations for Defuelling and Decommissioning are well advanced and the site will continue to draw on the experience of other Magnox sites to develop opportunities for innovation and acceleration within its Decommissioning programme.Defuelling and Decommissioning
Following cessation of generation on 31 December 2006, the process of Defuelling Sizewell A's twin reactors has begun. After removing the spent fuel from each of the two reactors, the elements are safely packaged within secure flasks then despatched to Sellafield in Cumbria for reprocessing. This work will take approximately two and a half years to complete. Around 53,000 individual fuel elements will be removed from Sizewell A’s reactors.